West Gate Tunnel saga shows risk of 'lock-in' on mega-projects pitched by business

  • Written by: James Whitten, Ph.D Candidate, Faculty of Architecture, Building and Planning, University of Melbourne
The Conversation

Victoria’s government finds itself in a big hole with its West Gate Tunnel project. As diggers lie idle in a dispute over what to do with contaminated soil, it’s facing long delays and billions in extra costs. But the government appears locked into a contentious project that was put to it as a market-led proposal, an arrangement that bedevils transport projects across Australia.

Australian governments look increasingly to mega-projects to solve urban and regional transport problems. These projects are city-shaping. They can transform how entire urban regions function.

The public has a clear stake in these projects, but unsolicited market-led proposals are subverting planning processes that are meant to protect the public interest.

Read more: Market-led infrastructure may sound good but not if it short-changes the public

Market-led proposals are unsolicited bids to government by private firms to provide public services or infrastructure. Policies governing market-led proposals were introduced in 2014 and 2015 by state governments across Australia to promote innovation in service delivery and value for money for taxpayers.

The increasing use of market-led proposals for transport mega-projects raises important questions. How are policies governing these managed, to what end, and for whose benefit?

In Melbourne, the tensions between toll road operator Transurban and the Victorian government over the West Gate Tunnel highlight a fundamental shortcoming of market-led proposals. Bluntly, these are not suited to the planning of transport mega-projects because governments can become “locked in” with questionable benefits. Lock-in has been defined as “the escalating commitment of decision-makers to an ineffective course of action”.

The case of the West Gate Tunnel

Transurban’s builders of the West Gate Tunnel, John Holland and CPB Contractors, laid off 137 workers last month in a dispute about liability for contaminated soil. This is bad press for the state government, which touted job creation and training as key project benefits.

The dispute could add to delays and costs on top of two earlier changes related to the project. The first was a ten-year extension to Transurban’s CityLink tolling concession that will cost road users billions of dollars. The second was an increase in construction costs from A$5.5 billion to A$6.7 billion to extend tunnels to save a public park.

Explanations for the dispute include the Environmental Protection Authority tightening soil disposal requirements, difficulties determining site conditions during the environmental assessment process, and insufficient foresight and planning for these risks.

Another explanation for what happened is “lock-in”. Evidence of lock-in on the West Gate Tunnel points to deeper systemic problems with market-led proposals for transport mega-projects in general.

How does lock-in happen?

Lock-in can occur when powerful corporations partner with governments in circumstances that enable them to exploit vulnerabilities in our public institutions. Some of these vulnerabilities include increasing reliance by governments on private finance, and the short period between elections compared to the time it takes to deliver bold public works programs.

Lock-in happens when the real decision to build a project is made well in advance of processes that are publicly declared to inform that decision. Once governments are locked in to a project, it can make alternatives appear increasingly unviable, if not unthinkable.

There is strong evidence to suggest this happened with the West Gate Tunnel. Significant concerns were raised early on that the project might not provide its claimed public benefits.

Read more: Impending traffic chaos? Beware the problematic West Gate Tunnel forecasts

What makes market-led proposals different?

Market-led proposals differ from government-led projects because planning is effectively outsourced to the private sector.

Market-led proposals also differ from public-private partnerships, like Melbourne’s CityLink tollway. In such cases, government plans these projects, but private firms deliver and operate them. (At least CityLink was part of a long-standing, if largely discredited, strategic plan.)

Revelations that Transurban acted in secretive and strategic ways to secure support for its West Gate Tunnel raise serious ethical questions. What does it mean to be a “good partner” to government? How should powerful private corporations obtain a “social licence” to operate?

These questions draw attention to problems inherent in Victoria’s opaque market-led proposal process. The government’s caution about the AirRail consortium’s unsolicited bid for Melbourne’s airport rail link points toward some of these dangers.

Read more: Transurban's West Gate tollway is a road into uncharted territory

What’s wrong with this approach?

Government policies for assessing market-led proposals give powerful private firms like Transurban influence over strategic planning. This contrasts with the relatively limited influence granted to affected communities and stakeholder groups advocating for sustainable transport solutions.

Acceptance of Transurban’s bid allowed a multi-billion-dollar toll road to override plans that had been taken to an election. These plans were simpler and far less expensive. The plans had been developed with the local community to better manage freight traffic by upgrading access to existing freeways.

The West Gate Tunnel process involved expedited planning that bypassed broad-based community consultation. John Holland and CPB Contractors were selected in April 2017 “to get to work” on the project. That was five months before public hearings concluded in September. Over 500 submissions were received.

Add to this the suppression of independent and critical oversight and a heavily redacted business case, and a very concerning picture of Victoria’s market-led process emerges.

Read more: Sidelining citizens when deciding on transport projects is asking for trouble

Wanted: an integrated transport plan

Because governments are ultimately responsible for their partnerships, the Victorian government should demonstrate stronger accountability and leadership. Victorians are still waiting for an integrated transport plan, as is required to be prepared under the 2010 Transport Integration Act. Instead of outsourcing transport problems to private firms, the government should develop a statewide, genuinely consultative, evidence-based plan.

An integrated transport plan would allow Victorians to see how future mega-projects, regardless of who proposes them, might serve everyone’s interests.

Authors: James Whitten, Ph.D Candidate, Faculty of Architecture, Building and Planning, University of Melbourne

Read more https://theconversation.com/west-gate-tunnel-saga-shows-risk-of-lock-in-on-mega-projects-pitched-by-business-131210

Business News

The Rise of Digital Marketplaces in the Australian Trade Sector

For decades, the Australian trade and construction sector operated almost entirely on word-of-mouth recommendations and local community networks. Small business owners typically relied on local newspa...

Daily Bulletin - avatar Daily Bulletin

How Immigration Lawyers Can Help

Introduction Visa decisions can shape employment, family life, study plans, travel, and future residence. A small omission can lead to delay, added expense, or refusal. Immigration lawyers assess l...

Daily Bulletin - avatar Daily Bulletin

How Industrial Drying Equipment Supports Efficient Processing

Many industrial processes require moisture to be removed from compressed air, products or process materials before they move to the next stage. Excess moisture can affect equipment performance, produc...

Daily Bulletin - avatar Daily Bulletin

Practical Ways a Whiteboard Can Improve Workplace Communication

Effective communication helps teams stay organised, share ideas and keep track of important information. While digital tools are now common in many workplaces, a whiteboard continues to provide a simp...

Daily Bulletin - avatar Daily Bulletin

Designing Eco-Friendly Custom Water Bottles for Your Next Event

The Evolution of Sustainable Event Merchandise Event planning has undergone a massive transformation over the last decade. Gone are the days when organizers could hand out cheap, single use plastic...

Daily Bulletin - avatar Daily Bulletin

Why Choosing a Professional Florist Melbourne Makes Flower Delivery Impactful

Flowers have a great power to speak when humans cannot express their feelings with right words. Flowers are the best gifts when you are celebrating a birthday or welcoming a newborn child into your fa...

Daily Bulletin - avatar Daily Bulletin

The Business Case for Choosing Australian Fabricators Over Imported Alternatives

For a long time, you might have defaulted to overseas suppliers when sourcing fabricated metal components for a project. The unit price was lower on paper, and the maths seemed straightforward. That...

Daily Bulletin - avatar Daily Bulletin

Australian organisations are relying on business continuity plans built for a far more predictable world

Tariff escalations, supply chain fragility, geopolitical events, and the ongoing threat of cyber disruption have reshaped the risk environment facing Australian organisations. The problem is that ma...

Daily Bulletin - avatar Daily Bulletin

How to Rent a Car for Uber in Melbourne: What Every New Driver Needs to Know

Starting out as an Uber driver in Melbourne is not as complicated as it sounds but getting the vehicle right is where most new drivers get stuck. Uber has strict requirements around vehicle age, condi...

Daily Bulletin - avatar Daily Bulletin

The Daily Magazine

How Long Does a Solar Home Battery Last? LFP Cycles and Warranty Explained

A battery does not usually reach its advertised cycle count and suddenly stop working. Capacity ch...

How to Hire a Nanny: A Complete Guide for Families

Finding the right childcare professional can make everyday family life easier and give parents gre...

The Blue-Collar Shortage Employers Can't Solve With More Applicants

Australia's hiring market has cooled considerably since the post-pandemic frenzy of 2021 and 2022. F...

The Playground as Classroom: How Line Markings Are Reinforcing What Students Learn Inside

For a long time, the playground was treated as a break from learning rather than part of it. A place...

How Technology Is Changing the Way Gardens Are Maintained

Garden maintenance has always been a hands on ritual. Mowing on a schedule, watering by instinct, an...

One Blocked Drain Can Become a Whole House Plumbing Problem: How It Happens

A blocked hand basin feels local. So does a slow shower. Homeowners naturally focus on the fixture...

AI in Marketing: From Experiment to Everyday Tool

For the past couple of years, artificial intelligence in marketing has mostly lived in the "let's se...

What Businesses Can Do to Make Sustainability More Practical Day to Day

Sustainability can sound like a huge corporate project, something tied to annual reports, long-term ...

The Hidden Logistics Behind a Smooth-Running Construction Site

A construction site can look chaotic from the outside. There are machines moving in different direct...