WestConnex audit offers another $17b lesson in how not to fund infrastructure

  • Written by: Marion Terrill, Transport Program Director, Grattan Institute

The way we throw money at major transport projects almost guarantees billions of Australian taxpayers’ dollars are wasted. Australian Auditor-General Grant Hehir has released yet another damning report on the process behind the A$16.8 billion investment in Sydney’s WestConnex motorway, Australia’s biggest infrastructure project since the Sydney Harbour Bridge.

WestConnex joins the long list of big, bungled transport investment decisions by Australian governments, both federal and state.

Analysis by the Grattan Institute shows these blunders are more than unfortunate accidents. They’re symptoms of a reckless infrastructure investment process, which has been showing up in a pattern of cost blowouts.

What did the audit reveal?

Both the Coalition and the then Labor government went to the 2013 federal election promising to spend at least A$1.5 billion on WestConnex – before any business case had been completed. Voters were not informed of the project’s investment merits until 2014, when Infrastructure Australia first published the business case.

image Auditor-General Grant Hehir has found the main reason initial WestConnex funding was set up as a concessional loan was to make the federal budget look better. ANAO

The primary justification for funding early expenses with a concessional loan – the first of its kind – rather than a grant was flimsy. The audit report found the decision was made because this approach would have “a smaller impact on the presentation of the Australian Government Budget”. In other words, it would look better on the books.

Sadly, recklessness of this magnitude is not new, or unique to mega-projects. Grattan analysis of the Deloitte Investment Monitor shows that between 2000 and 2015 more than one-third of transport infrastructure projects were committed to them before a formal funding commitment had been made.

This matters, because poorly planned projects cost more than they should.

The audit of WestConnex found that the hasty early investment in the project was structured in a way that did not deliver value for money to Australian taxpayers. The A$2 billion concessional loan was made at below market rates, structured in a way that minimised the tax paid on the interest, and the time before interest is due to be paid to the government on the loan was set to be four times longer than major lenders traditionally provide.

Poor process is the norm

WestConnex is not unique in this way. The Grattan analysis of the projects built between 2000 and 2015 found that if a project was promised before a formal funding commitment had been made, it was more likely than not to run over budget. And when these overruns occurred, they were massive – project costs doubled, on average.

But committing to projects before checking if their investment merits stack up is not the only problem with how our governments invest in transport infrastructure. When business cases are completed, these are not done using comparable methodologies across jurisdictions. They are also rarely made available for the public to scrutinise.

When projects are opened, politicians use the phrase “finished on budget” very loosely. For instance, Perth’s Peel Deviation project was declared “on budget” despite costing five times the initial estimate. Why? Because at one point close to project completion, another estimate put the cost even higher.

Sometimes, projects are backed for base political reasons, rather than on their investment merits. For instance, the Princess Highway Duplication project in Victoria’s western district was found to offer only eight cents of benefit for every dollar spent. But it runs through the highly marginal federal seat of Corangamite – so it was built anyway.

Key steps to better spending

So, what should be done to ensure public money is better spent?

A good place to start would be to make infrastructure spending decisions more transparent. This could be done by publishing the full details of a project’s estimated and realised costs and return on investment on data.gov.au. Infrastructure spending should also be included in the Productivity Commission’s annual Report on Government Services.

Second, the quality of business cases needs to be lifted, substantially and quickly. The Commonwealth should ensure one agreed method is used to measure and manage project risk. The Productivity Commission should assign “reliability ratings” to infrastructure business cases, which should be published on Infrastructure Australia’s website for all to see.

Finally, taxpayers should demand that politicians fully evaluate a project’s investment merits before they commit to funding it.

The auditor-general has found politicians committed A$17 billion to WestConnex as if it were pocket change. This happy-go-lucky approach is fine for kids deciding to buy a treat on the way home from school. But when it comes to spending billions of dollars of public money on projects designed to last for generations, we need to insist on something better.

Authors: Marion Terrill, Transport Program Director, Grattan Institute

Read more http://theconversation.com/westconnex-audit-offers-another-17b-lesson-in-how-not-to-fund-infrastructure-73206

Business News

How Immigration Lawyers Can Help

Introduction Visa decisions can shape employment, family life, study plans, travel, and future residence. A small omission can lead to delay, added expense, or refusal. Immigration lawyers assess l...

Daily Bulletin - avatar Daily Bulletin

How Industrial Drying Equipment Supports Efficient Processing

Many industrial processes require moisture to be removed from compressed air, products or process materials before they move to the next stage. Excess moisture can affect equipment performance, produc...

Daily Bulletin - avatar Daily Bulletin

Practical Ways a Whiteboard Can Improve Workplace Communication

Effective communication helps teams stay organised, share ideas and keep track of important information. While digital tools are now common in many workplaces, a whiteboard continues to provide a simp...

Daily Bulletin - avatar Daily Bulletin

Designing Eco-Friendly Custom Water Bottles for Your Next Event

The Evolution of Sustainable Event Merchandise Event planning has undergone a massive transformation over the last decade. Gone are the days when organizers could hand out cheap, single use plastic...

Daily Bulletin - avatar Daily Bulletin

Why Choosing a Professional Florist Melbourne Makes Flower Delivery Impactful

Flowers have a great power to speak when humans cannot express their feelings with right words. Flowers are the best gifts when you are celebrating a birthday or welcoming a newborn child into your fa...

Daily Bulletin - avatar Daily Bulletin

The Business Case for Choosing Australian Fabricators Over Imported Alternatives

For a long time, you might have defaulted to overseas suppliers when sourcing fabricated metal components for a project. The unit price was lower on paper, and the maths seemed straightforward. That...

Daily Bulletin - avatar Daily Bulletin

Australian organisations are relying on business continuity plans built for a far more predictable world

Tariff escalations, supply chain fragility, geopolitical events, and the ongoing threat of cyber disruption have reshaped the risk environment facing Australian organisations. The problem is that ma...

Daily Bulletin - avatar Daily Bulletin

How to Rent a Car for Uber in Melbourne: What Every New Driver Needs to Know

Starting out as an Uber driver in Melbourne is not as complicated as it sounds but getting the vehicle right is where most new drivers get stuck. Uber has strict requirements around vehicle age, condi...

Daily Bulletin - avatar Daily Bulletin

When Should You Speak to a Lawyer About a Legal Issue?

Legal issues can begin with a simple question, then become harder to manage once formal steps are involved. Many people wait until a matter feels urgent before seeking guidance, even though earlier ...

Daily Bulletin - avatar Daily Bulletin

The Daily Magazine

How Long Does Interstate Freight Take in Australia?

If you have ever arranged for stock, equipment or materials to travel from one Australian state to a...

How AEC Firms Can Scale Faster Without Sacrificing Project Quality

Growth presents a fundamental dilemma for architecture, engineering, and construction firms: expan...

What Makes an Aesthetic Clinic Worth Going Back To?

Trying an aesthetic clinic for the first time can feel like a bit of a gamble. You can read review...

Elevate Your Morning Routine with Cafe-Style Coffee at Home with the Right Coffee Machine

There's something magical about that first sip of coffee in the morning. It’s more than just a bev...

Top Garment Steamers for Busy Professionals in Australia

The gap between garment steamers built for a quick touch-up and ones built to keep pace with a wor...

Correct Sleeping Posture to Minimize Back Strain

Most people don’t pay much attention to how they sleep until they start waking up with a stiff bac...

Why Product Longevity Matters for Sustainable Australian Buildings

Sustainability in building design is often associated with recycled materials, renewable resources a...

NDIS Support Coordination Explained: What Does a Support Coordinator Actually Do?

NDIS support coordination explained means understanding how a professional can help participants n...

When Should You Speak with Divorce Lawyers in Sydney?

Divorce involves more than completing an online application. It can affect parenting arrangements, p...